CPUT-ENGINEERING

Scope of work:

• Demolition.

• Internal Alteration, Drywall partitioning, Walls and ceilings painting

• Electrical upgrade of entire floor approximately 1 400 m2 floor area

• Floor replacement, Doors replacement including ironmonger.

• Light fittings replacement and electrical power skirtings installation.

• Manufacturing and installation of new computer Lab desks.

• Repairs of hollow plastered walls and concrete spalling.

• Repair to plumbing and installation of new staff kitchen.

➢ Project duration: 7 weeks

BEFORE
AFTER
CPUT-GRANGER-BAY
Scope of work:

• Floor replacement

• walls and ceiling painting

• Light fittings replacement and electrical re-wiring.

• Auditorium seat re-upholstery.

• Roof waterproofing

• Repairs of hollow plastered walls and concrete spalling.

➢ Project duration: 6 weeks

BEFORE
AFTER
CPUT-AND-UCT
Scope of work:

•  Walls, Doors, door frames, and skirtings refurbishment.

➢ Project duration: 2 weeks

BEFORE
AFTER